General 28/11/2026 05:29 PM

ERS Tower Structure In Ranau Completed, Crossarm Installation Underway

BERNAMA Malaysian National News Agency
Share:
ERS Tower Structure In Ranau Completed, Crossarm Installation Underway
Kerja pembinaan menara sementara Sistem Pemulihan Kecemasan (ERS) giat dijalankan berhampiran runtuhan menara T313 hari ini. Fasa pertama pembinaan menara ERS bagi talian penghantaran 275 kilovolt (kV) ke Lupis, Segaliud selesai, manakala kerja seterusnya termasuk pemasangan kabel penahan bagi konduktor bawah dan menaikkan tiang utama secara manual sedang dilaksanakan.

KOTA KINABALU, Nov 28 (Bernama) -- The main structure of the temporary Emergency Restoration System (ERS) tower in Ranau was in place by 1.45 pm today, Sabah Electricity said.

The utility company said its technical team was now proceeding with the next phase, involving the installation of the tower’s crossarms and supporting components, before transmission cables could be installed.

“This development marks another important milestone in efforts to restore the electricity transmission link connecting Sabah’s West Coast and East Coast,” Sabah Electricity said in a statement today.

The company stressed that the safety of its personnel remained a priority at every stage of the operation as it sought to expedite electricity supply restoration.

Meanwhile, the Sabah Grid System Operator (GSO) team continued to manage and monitor the stability of the electricity supply system around the clock at the company’s control centre here.

“Following the incident involving transmission tower T313, the GSO team is balancing limited electricity generation capacity with consumer demand in Sabah’s East Coast,” the statement said.

It said continuous monitoring, precise decision-making and efficient system management ensured that available generation capacity was utilised optimally without compromising system stability.

Sabah Electricity expressed its appreciation to the entire GSO team for their dedication, professionalism and commitment in carrying out their duties and responsibilities.

Transmission tower T313, located on the banks of the Liwagu River in Kampung Sagindai Lama along the Ranau-Telupid Road, collapsed due to erosion of its foundation caused by continuous rain and strong currents from flooding of the Liwagu River.

The incident affected 153,599 registered consumers. Sabah Electricity is targeting electricity supply restoration by Dec 2 or earlier.

The public can follow the latest updates via Sabah Electricity Careline’s official Facebook page or contact 15444, 088-515000 or WhatsApp 019-8525427.

-- BERNAMA