KUALA LUMPUR, Nov 18 (Bernama) -- The reintroduction of the Variation of Price (VOP) clause to address rising diesel and bitumen costs will be subject to the Finance Ministry’s (MOF) official requirements, including its scope, eligibility criteria and procedures.
Works Minister Datuk Seri Alexander Nanta Linggi said that his ministry would provide the necessary cooperation on matters within its jurisdiction to ensure that challenges faced by players in the construction industry could be addressed.
“The government has agreed to reintroduce the VOP clause specifically to address rising diesel and bitumen costs, as announced by Prime Minister Datuk Seri Anwar Ibrahim in Budget 2027.
“This reflects the government's concern over the challenges faced by the industry,” he said in his speech at the dinner held in conjunction with the Seventh Annual General Meeting of the Bumiputera Contractors Association of Malaysia (PKBM) at the World Trade Centre Kuala Lumpur here tonight.
He acknowledged that the construction industry was currently facing various challenges, particularly rising building material and operating costs, as well as cash flow pressures.
Continuous engagement between the government and industry players is crucial to ensuring that challenges on the ground are properly understood and addressed.
Nanta added that the government remained committed to expanding opportunities for Bumiputera contractors to participate in the country's development, including by increasing the value of government procurement allocated to G1 to G4 contractors.
“The procurement allocation has increased to RM7.5 billion for 2027, compared with RM4 billion this year, thereby creating greater opportunities for Bumiputera contractors to participate in government projects,” he said.
The Works Ministry has also been allocated RM10.882 billion under Budget 2027, including RM9.736 billion for development expenditure, with a focus on implementing high-impact infrastructure projects, maintaining federal roads, and improving road safety and user comfort.
He said the ministry would continue to strengthen project implementation monitoring, including taking intervention measures to address project delays.
Meanwhile, PKBM president Datuk Seri Dr Azman Yusoff hoped that the allocation of government projects to Bumiputera contractors, particularly those in Grades G1 to G4, would be carried out transparently, fairly and comprehensively to ensure that qualified contractors could fully benefit from the opportunities provided.
He said the allocation of projects through ballot-based selection and quotation exercises should adhere to the prevailing government procurement procedures to help small contractors build their track records, strengthen their financial positions and expand their business capacity.
He also hoped that newly appointed concessionaires would be given clear responsibilities to empower Bumiputera contractors, particularly by providing them with suitable opportunities in maintenance works, minor works and ballot-based projects.
“The involvement of Bumiputera contractors in the implementation of these projects should be continuous and deliver a meaningful economic impact to local industry players,” he said.
The event was attended by about 350 guests, comprising representatives from ministries and government agencies, construction industry players, as well as Bumiputera contractors from across the country.