Construction Of PDF By Lynas Malaysia 79 Percent Completed As Of Oct 31 - Mohammad Yusof

BERNAMA Malaysian National News Agency
Share:
Construction Of PDF By Lynas Malaysia 79 Percent Completed As Of Oct 31 - Mohammad Yusof
Timbalan Menteri Sains, Teknologi dan Inovasi, Datuk Dr Mohammad Yusof Apdal.

KUALA LUMPUR, Nov 18 (Bernama) -- The construction of the Permanent Disposal Facility (PDF) for radioactive waste by Lynas Malaysia Sdn Bhd reached 79 percent as of October 31, with 1.46 million metric tonnes of Water Leach Purification (WLP) waste having been transferred to the facility.

Deputy Minister of Science, Technology and Innovation Datuk Dr Mohammad Yusof Apdal stated that the transfer of waste from the temporary storage facility (RSF) to the PDF is regularly monitored by the Atomic Energy Department (JTA) to ensure radiation safety for the public and the environment.

"JTA has conducted environmental monitoring and sampling. This monitoring data can also be accessed by the public in real-time through the MOSTI (Ministry of Science, Technology and Innovation) website and https://erms.atom.gov.my," he said.

He said this when winding up the committee-stage debate on the Supply (Budget) Bill 2027 and the Motion for Development Expenditure Estimates 2027 for MOSTI in the Dewan Rakyat today.

Mohammad Yusof said the extension of Lynas' license period for 10 years was made based on technical, legal, and comprehensive compliance assessments by JTA, in addition to being subject to stricter license conditions under the Atomic Energy Licensing Act 1984 [Act 304].

He said that within the first five years, Lynas must modify the processes at its plant using low-temperature methods to reduce the activity concentration of WLP waste to below the control limits of Act 304.

"In the event of non-compliance with the imposed conditions, license suspension or revocation action can be implemented by JTA at any time under the provisions of the Atomic Energy Licensing Act 1984 [Act 304]," he said.

Additionally, Mohammad Yusof stated that any rare earth element (REE) processing activity anywhere containing naturally occurring radioactive material with an activity concentration exceeding one becquerel per gram (Bq/g) is subject to JTA licensing and regulation, regardless of the investor or technology source.

Regarding the nation's preparedness in nuclear energy and technology, including aspects of Small Modular Reactors (SMR), he said MOSTI is drafting a National Nuclear Talent Development Plan to strengthen human capital development in line with technological developments and future needs.

Mohammad Yusof said that although the use of SMRs is not explicitly stated in the National Nuclear Technology Policy (DTNN) 2030, the ministry continues to support talent development in the field through various initiatives, including the preparation of such talent development plans.

"MOSTI, through the Malaysian Nuclear Agency, has also completed a preliminary study regarding the Multipurpose Reactor (MPR) and is currently drafting a blueprint as a strategic planning basis for the period from 2026 to 2030," he said.

He stated that the blueprint is drafted under the Fourth Strategic Core of DTNN as a guideline for medium-and long-term planning before the development of the facility is realised.

The Dewan Rakyat subsequently approved the operating and development expenditure estimates for 2027 amounting to RM1,292,392,000 allocated to MOSTI under Budget 2027 with a voice vote in agreement, after being debated by 19 Members of Parliament.

The session continues tomorrow.