KUALA TERENGGANU, Nov 16 (Bernama) -- The transit-oriented development (TOD) project at the East Coast Rail Link (ECRL) station in Jertih, estimated at RM16 million, is currently coordinating project requirements and preparing for procurement ahead of construction.
Terengganu Infrastructure, Utilities and Rural Development Committee chairman Datuk Hanafiah Mat said the Terengganu Public Works Department (JKR) had received a proposed scope of work for the TOD project from the Besut District Council.
"Several coordination meetings have been held at both district and state levels, involving the Terengganu JKR, the State Economic Planning Unit, as well as relevant departments and agencies.
"Terengganu JKR is now in the process of preparing the Government Requirements document to identify, coordinate and document the project requirements clearly before the design is finalised," he said during a question-and-answer session at the Terengganu State Legislative Assembly sitting at Wisma Darul Iman here today.
He was responding to a question from Dr Riduan Mohamad Nor (PAS-Jertih) on the progress of the TOD project at the Jertih ECRL station.
Hanafiah said the project procurement process was scheduled to begin on Nov 26, while the Letter of Acceptance was expected to be issued on March 1 next year.
He said the project, estimated to take 24 months to complete, would involve building a transit terminal, installing solar-powered street lights, and providing a surau, guardhouse, kiosks for rent and a drainage system.
The ECRL, which is scheduled to begin operations in the middle of next month, is expected to shorten travel times between the East Coast and the Klang Valley, with journeys from Gombak to Kuala Terengganu taking about three hours and from Gombak to Kota Bharu around four hours.
The ECRL line in Terengganu covers 242km and includes six stations: Chukai, Kemasik, Dungun, Kuala Terengganu, Bandar Permaisuri, and Jertih.